Question 14008 of 844 · Washington 01 Journey Level Electrician Exam

When the relationship between a contractor and its designated administrator ends, how soon must the contractor notify the department in writing?

Exactly one answer is correct.

Show solution

Correct answer to question 14008

  • B: Within 10 days

Explanation

RCW 19.28.061 requires written notification to the department within 10 days after the administrator or master electrician relationship terminates. The contractor then has a limited period to designate a replacement.