Question 14063 of 844 · Washington 01 Journey Level Electrician Exam

How many Class B labels may be used on one job site per week?

Exactly one answer is correct.

Show solution

Correct answer to question 14063

  • B: Two labels

Explanation

WAC 296-46B-908 limits Class B basic electrical work to no more than two labels per week on any one job site. Larger scopes require a regular permit.