Question 14075 of 844 · Washington 01 Journey Level Electrician Exam

In what order are claims against an electrical contractor's bond paid?

Exactly one answer is correct.

Show solution

Correct answer to question 14075

  • C: Labor, materials and equipment, taxes, then damages

Explanation

RCW 19.28.071 sets payment priority to employees for labor, then for materials and equipment, then for taxes and contributions, and finally for damages. The surety's liability is capped at the bond amount.