Question 10059 of 1033 · Washington 01 Journey Level Electrician Exam
When the 120 percent rule is used for a load-side interconnection, where must the backfed breaker be located?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 10059
- D: At the opposite end of the busbar from the main supply OCPD
Explanation
The 120 percent allowance requires the PV backfed breaker to be positioned at the end of the busbar opposite the primary supply. This prevents any part of the busbar from carrying more than its rating.
More questions: Special Equipment, Pools, PV and EV
- 10060An inverter has a maximum continuous output current of 32 amperes. What is the minimum rating of the OCPD for the inverter output circuit?
- 10061A PV interconnection made between the service meter and the service disconnecting means is what type of connection?
- 10062For a stationary energy storage system at a one- or two-family dwelling, where must the disconnecting means or its remote control be located?
- 10063Article 706 applies to permanently installed energy storage systems with a capacity greater than what amount?
- 10064What protection is required for receptacles installed for the connection of EV charging equipment?
- 10065An EVSE has a maximum load of 48 amperes. What is the minimum OCPD rating for the branch circuit supplying it?