Question 14006 of 844 · Washington 01 Journey Level Electrician Exam
May a city or county in Washington require an electrical contractor licensed by the state to obtain a separate local electrical contractor license or bond?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 14006
- C: No, state licensing preempts local license and bond requirements
Explanation
RCW 19.28.041 provides that political subdivisions may not require a state licensed electrical contractor to obtain any additional license or bond for electrical contracting. Local jurisdictions may still run their own permit and inspection programs.
More questions: Washington Laws and Rules
- 14007A certified administrator may be designated by how many electrical contractors at the same time?
- 14008When the relationship between a contractor and its designated administrator ends, how soon must the contractor notify the department in writing?
- 14009If a contractor's designated administrator leaves the company, the contractor license becomes void unless a new qualifying person is designated within how many days?
- 14010If the designated master electrician of a contractor dies, how long does the contractor have to designate a new master electrician or administrator before the license becomes void?
- 14011A Washington electrical administrator certificate is renewed on what schedule?
- 14012How many hours of approved continuing education must a Washington electrician complete for each year of the certification period?