Question 14006 of 844 · Washington 01 Journey Level Electrician Exam

May a city or county in Washington require an electrical contractor licensed by the state to obtain a separate local electrical contractor license or bond?

Exactly one answer is correct.

Show solution

Correct answer to question 14006

  • C: No, state licensing preempts local license and bond requirements

Explanation

RCW 19.28.041 provides that political subdivisions may not require a state licensed electrical contractor to obtain any additional license or bond for electrical contracting. Local jurisdictions may still run their own permit and inspection programs.