Question 6072 of 966 · Washington 01 Journey Level Electrician Exam

When must a raceway system be complete relative to pulling conductors?

Exactly one answer is correct.

Show solution

Correct answer to question 6072

  • D: Between outlets and junction points before conductors are installed

Explanation

Raceways must be installed complete between outlet, junction, or splicing points before conductors are pulled in. Prewired raceway assemblies are an exception where specifically permitted. See 300.18(A) in NEC 2020 and 2023 and 300.20(A) in NEC 2026.