Question 14051 of 844 · Washington 01 Journey Level Electrician Exam

After an inspector notifies an installer of a code violation, within how many days must the correction be made?

Exactly one answer is correct.

Show solution

Correct answer to question 14051

  • C: 15 days

Explanation

RCW 19.28.101 and WAC 296-46B-901 require corrections to be made within 15 calendar days after notification of the violation. Failure to correct can lead to penalties.