Question 14051 of 844 · Washington 01 Journey Level Electrician Exam
After an inspector notifies an installer of a code violation, within how many days must the correction be made?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 14051
- C: 15 days
Explanation
RCW 19.28.101 and WAC 296-46B-901 require corrections to be made within 15 calendar days after notification of the violation. Failure to correct can lead to penalties.
More questions: Washington Laws and Rules
- 14052May electrical wiring be concealed before it has been inspected and approved?
- 14053Before electrical work begins, where must the electrical permit or permit number be posted?
- 14054An electrical permit generally covers how many job sites?
- 14055Unless extended, when does a Washington electrical work permit expire?
- 14056After completing work, an installer must request inspection within how many working days?
- 14057A contractor energizes part of a new installation. Within how many working days must inspection be requested?