Question 14055 of 844 · Washington 01 Journey Level Electrician Exam
Unless extended, when does a Washington electrical work permit expire?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 14055
- A: One year after purchase
Explanation
WAC 296-46B-901 provides that electrical work permits expire one year after purchase unless the department has approved an extension. Inspection should be requested promptly after the work is done.
More questions: Washington Laws and Rules
- 14056After completing work, an installer must request inspection within how many working days?
- 14057A contractor energizes part of a new installation. Within how many working days must inspection be requested?
- 14058A contractor installs a provisional label in an emergency. Within how many working days must a permit be obtained?
- 14059Under RCW 19.28.006, replacing a 20 ampere receptacle like in kind is an example of which type of work?
- 14060Which of these is defined as Class B basic electrical work?
- 14061What does like in kind mean in the definitions of RCW 19.28.006?