Question 14058 of 844 · Washington 01 Journey Level Electrician Exam

A contractor installs a provisional label in an emergency. Within how many working days must a permit be obtained?

Exactly one answer is correct.

Show solution

Correct answer to question 14058

  • B: Two working days

Explanation

WAC 296-46B-901 and 296-46B-907 require a permit to be obtained, or the contractor portion of the label returned, within two working days after a provisional label is used. Only licensed contractors may use provisional labels.