Question 14058 of 844 · Washington 01 Journey Level Electrician Exam
A contractor installs a provisional label in an emergency. Within how many working days must a permit be obtained?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 14058
- B: Two working days
Explanation
WAC 296-46B-901 and 296-46B-907 require a permit to be obtained, or the contractor portion of the label returned, within two working days after a provisional label is used. Only licensed contractors may use provisional labels.
More questions: Washington Laws and Rules
- 14059Under RCW 19.28.006, replacing a 20 ampere receptacle like in kind is an example of which type of work?
- 14060Which of these is defined as Class B basic electrical work?
- 14061What does like in kind mean in the definitions of RCW 19.28.006?
- 14062Replacing a motor of what size is still Class A like in kind work under RCW 19.28.006?
- 14063How many Class B labels may be used on one job site per week?
- 14064Class B work is allowed for replacing furnaces with what maximum rating?