Question 14057 of 844 · Washington 01 Journey Level Electrician Exam
A contractor energizes part of a new installation. Within how many working days must inspection be requested?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 14057
- D: One working day
Explanation
WAC 296-46B-901 requires an inspection request within one working day after any portion of the installation is energized. Otherwise the request is due within three working days after completion.
More questions: Washington Laws and Rules
- 14058A contractor installs a provisional label in an emergency. Within how many working days must a permit be obtained?
- 14059Under RCW 19.28.006, replacing a 20 ampere receptacle like in kind is an example of which type of work?
- 14060Which of these is defined as Class B basic electrical work?
- 14061What does like in kind mean in the definitions of RCW 19.28.006?
- 14062Replacing a motor of what size is still Class A like in kind work under RCW 19.28.006?
- 14063How many Class B labels may be used on one job site per week?