Question 5062 of 844 · Washington 01 Journey Level Electrician Exam

An equipment bonding jumper on the load side of an OCPD is sized according to

Exactly one answer is correct.

Show solution

Correct answer to question 5062

  • B: Table 250.122 based on the largest OCPD supplying the circuits

Explanation

Load-side equipment bonding jumpers are sized from Table 250.122 based on the rating of the largest OCPD supplying circuits within the raceway or enclosure. See 250.102(D).